UK CBAM from 2027: what exporters to Britain need to know
The UK starts its own carbon border tax on 1 January 2027. Who pays, the £50,000 threshold, the first deadlines, and how it differs from the EU CBAM.
Checked against the rules on 22 November 2026.
The UK starts its own Carbon Border Adjustment Mechanism on 1 January 2027. Like the EU CBAM, it charges for the emissions embedded in imported carbon-intensive goods. If you export to both the EU and the UK, your buyers on both sides will ask for the same kind of data.
Goods covered
Aluminium, cement, fertiliser, hydrogen, and iron and steel. Glass and ceramics, proposed earlier, are not in scope from 2027.
Who pays
The importer of the goods into the UK is liable, not you. As with the EU, the cost comes back to you in price talks, and your buyer will ask for emissions data that lowers it.
The £50,000 threshold
An importer must register with HMRC once it imports £50,000 or more of CBAM goods in the previous 12 months, or expects to within the next 30 days. Only goods imported from 1 January 2027 count. Smaller UK buyers stay outside. Note the difference: the EU threshold is 50 tonnes a year, the UK one is a value.
Dates
- 1 January 2027: UK CBAM starts; the government publishes a rate per sector at the start of each quarter.
- 31 January 2028: registration deadline for importers who became liable in 2027 (normally 30 days).
- 31 May 2028: return and payment for the whole of 2027, the first accounting period.
- From 2028: quarterly accounting periods.
EU and UK side by side
| Topic | EU CBAM | UK CBAM |
|---|---|---|
| Starts | 1 January 2026 | 1 January 2027 |
| Who pays | Authorised CBAM declarant (importer) | Importer |
| Threshold | 50 tonnes a year | £50,000 of goods |
| Price | Certificates at the EU ETS price | Tax at a rate set each quarter |
| First payment | 30 September 2027, for 2026 | 31 May 2028, for 2027 |
Emissions data and carbon price paid
UK importers can use verified actual emissions or default values published by the government. They can also claim carbon price relief where the emissions were already subject to a qualifying carbon price. The UK has its own emissions and verification regulations: accreditation for another CBAM scheme does not automatically qualify a verifier for UK CBAM, and a verification report made for another CBAM scheme does not automatically count as a UK one. A verifier accredited for both can verify for both at the same time, so ask for a UK CBAM report as well (GOV.UK: getting the emissions intensity, 19 November 2026).
Which emissions count, and who can verify
The UK charge covers the direct emissions of the goods plus the emissions embedded in the precursor goods used to make them. Indirect emissions from electricity are left out at the start: the government has delayed them until 2029 at the earliest (GOV.UK CBAM factsheet).
Actual emissions must be verified by a verifier accredited for UK CBAM to ISO/IEC 17029:2019 and ISO 14065:2020, by an accreditation body that is a full member of the Global Accreditation Cooperation (Global ACI). Without verified figures, the importer uses the UK default value: one per good from 1 January 2027.
Rates and default values
Each quarter's rate is the average UK ETS auction price of the quarter before, reduced by the share of the sector's emissions covered by free allowances, so each sector has its own rate. HM Treasury's illustrative rates of 16 October 2026, on a UK ETS price of £58.15: iron and steel £9.69, aluminium £9.79, cement £8.78, fertilisers £1.45 and hydrogen £9.24 per tonne of CO2e. The real rates are published each quarter from 1 January 2027.
The UK default values are in a draft notice of the same date: one per 8-digit CN code for imports in 2027 and 2028, whatever the country of production, with a 10% mark-up except for fertilisers; from 2029, one per country. The UK CBAM checker shows the value for your code. A return filed on default values can never be amended to actual emissions (Finance Act 2026, Schedule 17, paragraph 8(2)), so your verified figure must reach your UK buyer before it files: for 2027, by 31 May 2028.
Two details of the threshold: the 30-day test counts only the goods imported in those 30 days, and the 12-month test is run on the first day of each month. And for cement, the UK covers every kaolinic clay of 2507 00 80, calcined or not; the EU covers only calcined clay.
What to do now
- Ask your UK buyers whether they expect to pass the £50,000 threshold.
- Work out your own figure with the emissions calculator; the same records serve both markets.
- Send UK buyers the emissions summary in English.
Sources: GOV.UK CBAM policy summary (updated 2 November 2026) and work out the date you'll need to register (16 July 2026); Finance Act 2026, Schedules 16 and 17. Contains public sector information licensed under the Open Government Licence v3.0.
General information for planning, not legal, tax or customs advice. See the disclaimer.